Wednesday 30 October 2013

Scaffold"s down



the top pic shows the progression from bare hebel at bottom - base render in middle and final colour on top half.
the second pic shows the front which hasn't been rendered as some work needs to be fixed on it, and the third pic is from other angle render has not been done on balcony area yet either.

Tuesday 22 October 2013

Lockup

lockup was on monday - Inspection went well, 2 issue's which SS has been helpful with and considering how well he addressed ones from frame inspection I have no doubt it will get sorted.

here is a pic from Saturday - our chippee J was just finishing off the gable façade


Scaffolding was meant to come down tomorrow but unfortunately melb weather has interfered big time as it has rained pretty much consistently since Monday...but it will happen soon enough, and now that inspection went well inside work should be happening soon :)
insulation first...then plaster yay!

Tuesday 15 October 2013

Render + Eaves

Render basecoat has been started they got heaps done :)
almost all bar the bottom 1/4 is basecoated



and eaves have been started hard to see in pic but they are there he could only do east side of house as wind was awful today.


Sparky has been - but couldn't get in will go soon to double check it all locations etc...

Monday 14 October 2013

Inside work

Been distracted...

more plumbing done inc fixing the mistake in powder room, shower bases in, bath framed, ducted heating roughed in, most external doors hung (wrong door handle on front door - not sure if that's a mistake or just temporary), hebel is finished so render will start soon.

Tuesday 8 October 2013

More pics


Solar hot water

Update - week 10

Sorry Mum been busy xxx

Second storey is wrapped - solar hot water unit has been installed, all bottom storey hebel is up including alfresco piers.
they had a hoist there today lifting hebel panels up to scaffolding was cool to see, lock up carpenter has been in straightening walls etc and I think waterproof plaster has been delivered as there was some blue sheeting stacked in laundry...but yesterday there was heap of workers on site which was cool and exciting to see :)

Thursday 3 October 2013

Scaffolding for second storey Hebel work is up

First floor hebel is 90% done now they were doing an alfresco pier when I was there at lunchtime - only 1 small section near the balcony wasn't up - and unsure now if they will be able to install that bit with the scaffolding up - will be there for about 3 weeks from what I was told, second storey should be wrapped on Monday and hebel finished off up there about a week or so later.