Tuesday, 19 November 2013

Stairs



have been too busy to really take proper pics at site sorry, but this is the staircase cant believe how light the house is, was overcast today and those windows face south...the stairs will be painted magnesium like the rest of the trim in the house...and carpeted for the kids safety...not flash but functional

Wednesday, 13 November 2013

Security, Plaster and Stairs

Security system is up onsite following some unsavoury cup day antics of local teens :(

Stairs are in but couldn't get a good pic, but happy to be locked out as it means so is everyone else!



Cornice is up - unsure if upstairs has been fully repaired but void platform is down so I believe 2 of the windows have had their arketraves installed too.
Below is kitchen and office boths pics taken from outside still


and here is blind colour I think we will go with...boring blinds but double rollers on front of house so we can let light in and have privacy still, and panels for sliding door


base coat of render has been finished apart from garage and front wall which still needs hebel looked at due to window issue...

Sunday, 3 November 2013

Plasterboard and bits

only a couple of pics - Friend of ours in kitchen, master bed and the roof trusses of garage up

Wednesday, 30 October 2013

Scaffold"s down



the top pic shows the progression from bare hebel at bottom - base render in middle and final colour on top half.
the second pic shows the front which hasn't been rendered as some work needs to be fixed on it, and the third pic is from other angle render has not been done on balcony area yet either.

Tuesday, 22 October 2013

Lockup

lockup was on monday - Inspection went well, 2 issue's which SS has been helpful with and considering how well he addressed ones from frame inspection I have no doubt it will get sorted.

here is a pic from Saturday - our chippee J was just finishing off the gable façade


Scaffolding was meant to come down tomorrow but unfortunately melb weather has interfered big time as it has rained pretty much consistently since Monday...but it will happen soon enough, and now that inspection went well inside work should be happening soon :)
insulation first...then plaster yay!

Tuesday, 15 October 2013

Render + Eaves

Render basecoat has been started they got heaps done :)
almost all bar the bottom 1/4 is basecoated



and eaves have been started hard to see in pic but they are there he could only do east side of house as wind was awful today.


Sparky has been - but couldn't get in will go soon to double check it all locations etc...

Monday, 14 October 2013

Inside work

Been distracted...

more plumbing done inc fixing the mistake in powder room, shower bases in, bath framed, ducted heating roughed in, most external doors hung (wrong door handle on front door - not sure if that's a mistake or just temporary), hebel is finished so render will start soon.